微软科隆数据中心因并网延迟启用燃气发电机
Rest of World报道称,微软位于墨西哥科隆的数据中心无法接入国家电网,并在运营首年的部分时间使用燃气发电机。微软在2023年提交给墨西哥环境部门的文件称,电网要到2027年年中才能全面供其使用,监管部门随后批准临时使用七台发电机。报道还指出,墨西哥已有150座数据中心,电网限制正促使部分运营商采用有时污染更高的替代能源。
科隆项目显示,人工智能和云服务推动的数据中心扩张可能快于电网建设,同时也引发化石燃料使用及企业 sustainability 承诺方面的疑问。
Behind a miles-long gray wall in the central Mexico town of Colón, a Microsoft data center portends the future for other data centers in the country. Unable to plug into the energy grid, it ran on gas-powered generators for at least part of the year.
That Mexico’s electric grid is struggling does not bode well for a country trying to position itself as a data center hub, and which is already home to 150 data centers, including from Microsoft, Amazon Web Services, and Google. Together, they have invested over $7 billion in the country since 2020.
Like Mexico, countries around the world are scrambling to meet the rising energy demands of data centers, spurred by a boom in artificial intelligence and cloud computing. Like Microsoft, some companies have tapped alternative — and sometimes more polluting — energy sources. Mexico’s power grid faces a deficitof 48,000 megawatt-hours by 2030, which is more than half the country’s output in 2023, according to the Mexican Institute For Competitiveness, a research center. As the country lures more data center-related investments, more companies may follow in Microsoft’s footsteps.