- Microsoft’s Colón data center runs on gas generators amid grid delays
Rest of World reported that Microsoft’s data center in Colón, Mexico, could not connect to the national grid and used gas-powered generators for at least part of its first year. Microsoft told Mexican environmental regulators in 2023 that the grid would not be fully available until mid-2027, and regulators later approved seven generators for temporary use. The report also says Mexico hosts 150 data centers and that grid constraints are prompting some operators to rely on alternative, sometimes more polluting energy sources.