Microsoft’s Colón data center runs on gas generators amid grid delays
Rest of World reported that Microsoft’s data center in Colón, Mexico, could not connect to the national grid and used gas-powered generators for at least part of its first year. Microsoft told Mexican environmental regulators in 2023 that the grid would not be fully available until mid-2027, and regulators later approved seven generators for temporary use. The report also says Mexico hosts 150 data centers and that grid constraints are prompting some operators to rely on alternative, sometimes more polluting energy sources.
Microsoft’s case illustrates how AI- and cloud-driven data-center expansion can outpace grid infrastructure, while also raising questions about fossil-fuel use and corporate sustainability commitments.
Behind a miles-long gray wall in the central Mexico town of Colón, a Microsoft data center portends the future for other data centers in the country. Unable to plug into the energy grid, it ran on gas-powered generators for at least part of the year.
That Mexico’s electric grid is struggling does not bode well for a country trying to position itself as a data center hub, and which is already home to 150 data centers, including from Microsoft, Amazon Web Services, and Google. Together, they have invested over $7 billion in the country since 2020.
Like Mexico, countries around the world are scrambling to meet the rising energy demands of data centers, spurred by a boom in artificial intelligence and cloud computing. Like Microsoft, some companies have tapped alternative — and sometimes more polluting — energy sources. Mexico’s power grid faces a deficitof 48,000 megawatt-hours by 2030, which is more than half the country’s output in 2023, according to the Mexican Institute For Competitiveness, a research center. As the country lures more data center-related investments, more companies may follow in Microsoft’s footsteps.