Nebius下调营收预期并加码AI建设

AI 总结

Nebius第三季度营收为9.81亿美元,同比增长571%,但受第三方数据中心延期影响,公司将2026年营收预期下调2亿美元至30亿美元,部分算力容量推迟至2027年上半年投运。公司计划在2027年投入400亿至450亿美元资本支出,预计全年营收为120亿至130亿美元,并在第四季度实现税前盈亏平衡。Nebius称,客户预付款及合约支持的资产融资将覆盖2027年支出的75%至85%;微软相关的新泽西州项目剩余容量预计于2027年第二季度交付。

深度见解

Nebius的营收与融资安排使其大规模AI基础设施扩张成为客户支持型融资的重要案例,而第三方项目延期也凸显了大型客户算力合同面临的执行风险。

In its third-quarter earnings call Thursday, the neocloud company Nebius laid out $40 billion in planned spending for 2027, far more than Wall Street had expected. It’s an ambitious plan, but it rests on a string of planned projects that are already starting to show cracks.

Nebius plans to fund the buildout by relying on customer pre-payments and loans backed by customer contracts — essentially using the future value of its data centers to finance their construction. But that can be a risky strategy if those projects get bogged down by delays or cancellations.

“Building at this scale is hard, and delays are part of our industry right now,” CEO Arkady Volozh said during Thursday’s earnings call. “We are not immune.”

The earnings announcement comes on the heels of reports that Microsoft is cooling on neocloud deals that aren’t delivering on time. That’s a problem for companies like Nebius, whose financing strategy is becoming more dependent on repayments. Because if it can’t get to capacity on time, it will keep piling on costs while revenues slip.

One of Nebius’s largest customers is Microsoft, which is paying for AI computing capacity at a Vineland, New Jersey data center that is now months behind schedule. Nebius’s contract with Microsoft is worth up to $19.4 billion, but it’s already letting deadlines slip. Only just over half of the Microsoft capacity is now planned for delivery by the end of the year, with the rest coming in Q2 2027. 

#Nebius#Microsoft#Meta#DataOne