Nebius cuts 2026 outlook as $40B–$45B AI buildout advances
Nebius reported third-quarter revenue of $981 million, up 571% from a year earlier, but cut its 2026 revenue forecast by $200 million to $3 billion after delays at third-party data-center sites pushed some capacity into the first half of 2027. The company plans $40 billion to $45 billion of 2027 capital expenditure and forecasts $12 billion to $13 billion in revenue for that year, with pre-tax break-even expected by the fourth quarter. It says customer prepayments and asset-backed financing will cover 75% to 85% of 2027 spending, while a delayed Vineland, New Jersey site serving Microsoft is expected to deliver its remaining capacity in the second quarter of 2027.
The outlook and financing plan make Nebius’s large-scale AI infrastructure build a material test of customer-backed funding, while delayed third-party capacity highlights execution risk around contracts with major customers such as Microsoft.
In its third-quarter earnings call Thursday, the neocloud company Nebius laid out $40 billion in planned spending for 2027, far more than Wall Street had expected. It’s an ambitious plan, but it rests on a string of planned projects that are already starting to show cracks.
Nebius plans to fund the buildout by relying on customer pre-payments and loans backed by customer contracts — essentially using the future value of its data centers to finance their construction. But that can be a risky strategy if those projects get bogged down by delays or cancellations.
“Building at this scale is hard, and delays are part of our industry right now,” CEO Arkady Volozh said during Thursday’s earnings call. “We are not immune.”
The earnings announcement comes on the heels of reports that Microsoft is cooling on neocloud deals that aren’t delivering on time. That’s a problem for companies like Nebius, whose financing strategy is becoming more dependent on repayments. Because if it can’t get to capacity on time, it will keep piling on costs while revenues slip.
One of Nebius’s largest customers is Microsoft, which is paying for AI computing capacity at a Vineland, New Jersey data center that is now months behind schedule. Nebius’s contract with Microsoft is worth up to $19.4 billion, but it’s already letting deadlines slip. Only just over half of the Microsoft capacity is now planned for delivery by the end of the year, with the rest coming in Q2 2027.