Create

Sign in to ReadmeX

or

How we handle your data: Privacy Policy

ReadmeX

Your AI reading companion

What would you like to catch up on?

Pick a briefing, or ask your own question.

Your community and people briefings stay personal to you.

Story

Microsoft Spent About $5 Billion Less Than Planned on Data Centers After Rental Delays

AI summary

Microsoft said last week that it spent about $5 billion less on capital expenditures in the third quarter than previously projected because data-center capacity it planned to rent was not ready on time. Microsoft did not publicly name the third parties behind the delays. The report identified cloud firm Iren as one of the parties associated with them.

AI 訂單沒取消,誰替延期付錢?

美國資料中心建置受電力與許可瓶頸影響,部分計畫延後。瀚亞投信 11 月 6 日指出,目前觀察主要是需求遞延,而非取消,但對已備料、擴產的台灣供應商而言,交貨往後移,支出未必能跟著停。

筆者認為「訂單還在」只回答了客戶是否仍要買,沒有回答這筆生意是否還划算。客戶需要調整時程,供應商就得算算多等幾個月,原本談好的利潤還剩多少?

訂單延後,供應商為何不能鬆口氣?

延期原因不能混在一起看,缺電、許可未過、客戶改設計與設備交期,各自牽涉不同責任,也影響廠商能否要求補償。

#Microsoft#Iren

Original · 4 min readRead the original
Group chat

No comments yet. Start the conversation.