US AI Data-Center Boom Faces Delivery and Financing Risks
36氪, citing Bernstein, reports that only about 170 GW of the 488 GW of announced US data-center capacity was considered likely to materialize, or roughly 35%. Other cited research points to inexperienced developers, lower projected on-time delivery and cost overruns, while EdgeCore reportedly raised its bond spread to 200 basis points and closed the offering at a 5.90% coupon after weak demand.
The report indicates that investors are demanding greater risk compensation for US AI data-center projects as uncertain completion, delays and higher costs become more visible.
最近,华尔街知名研究机构伯恩斯坦做了一项统计,结果挺让人意外。
美国已经公布的数据中心规划容量,累计高达488GW。但能把握落地的,只有约170GW,占比仅35%。
换句话说,美国规划中的数据中心,有接近三分之二,未来能不能建成还是个未知数。
更有意思的是,这些项目落不了地的原因,可谓五花八门。
有的开发商直接把数据中心当成房地产来搞,项目还没开工,土地就已经挂牌出售了;有的好不容易开工,客户却不断修改设计方案,硬生生让建设预算增加了近8亿美元。
以前,这些问题倒也不算什么。毕竟,AI是当下最火的投资方向。只要敢宣布几个GW的数据中心规划,华尔街就愿意给出高估值,银行和债券投资者也愿意掏钱。