谷歌接手Crusoe怀俄明州未完工数据中心
Crusoe确认已将其位于怀俄明州东南部的未完工数据中心项目出售给谷歌;谷歌此前曾对成本和建设周期提出担忧,接手后将负责开发。谷歌未披露交易价格,但计划投资170亿美元建设该园区;Crusoe与Tallgrass最初计划将其扩展至10吉瓦供电容量。
这笔交易让谷歌直接掌控一座大型AI基础设施园区,也凸显了设备、电力、成本和工期等超大规模数据中心建设难题。
Crusoe, an eight-year-old, Denver-based data center developer recently valued at $30.9 billion, confirmed Friday it has sold an unfinished data center project in southeastern Wyoming to Google.
Google, which Crusoe had tried and failed to land as a customer for the project, is taking over the development after reportedly raising concerns about its cost and construction timeline under Crusoe’s management.
Crusoe initially announced the project last year with Blackstone-backed infrastructure company Tallgrass, planning to eventually scale it to 10 gigawatts of power capacity.
Google did not disclose how much it paid Crusoe for the unfinished project, bu it announced plans to invest $17 billion to develop the data center campus.
The deal highlights how difficult it can be for independent data center developers to deliver massive projects on time and within budget, given the challenges of securing equipment and power. Growing opposition from local communities can further complicate development.
Despite taking over the Wyoming facility, Google hasn’t walked away from working with Crusoe entirely. Crusoe is developing another data center for Google near Amarillo, Texas.
#Google#Crusoe#Tallgrass#Google’s $17 billion Wyoming data center campus